We've finished manufacturing the first set of tunnel boring machines for the Hudson Tunnel Project. The machines are shipping to New Jersey now, and tunnel boring will start next year.
Read the full announcement here: www.gatewayprogram.org/wp-content/u...
We've finished manufacturing the first set of tunnel boring machines for the Hudson Tunnel Project. The machines are shipping to New Jersey now, and tunnel boring will start next year.
Read the full announcement here: www.gatewayprogram.org/wp-content/u...
Want to see more? Check out live feeds from our construction sites, plus more photos and videos, on our website: www.gatewayprogram.org
Want to see more? Check out live feeds from our construction sites, plus more photos and videos, on our website: www.gatewayprogram.org
Learn more at www.gatewayprogram.org/manhattan-tu...
Learn more at www.gatewayprogram.org/manhattan-tu...
🏗️ Five active construction projects
👷 20,000+ jobs
📈 $4.5 billion in economic output
Learn more at www.gatewayprogram.org
🏗️ Five active construction projects
👷 20,000+ jobs
📈 $4.5 billion in economic output
Learn more at www.gatewayprogram.org
Work is advancing at both ends of the NJ section of the new tunnel. The tunnel boring machine launch point is coming together in North Bergen, and we're now building the slurry wall for the Hudson County Shaft.
Work is advancing at both ends of the NJ section of the new tunnel. The tunnel boring machine launch point is coming together in North Bergen, and we're now building the slurry wall for the Hudson County Shaft.
Work on Tonnelle Ave is nearly complete! The final stages of construction involve finishing rock excavation and preparing to build the foundation and approach slab for the new bridge.
Work on Tonnelle Ave is nearly complete! The final stages of construction involve finishing rock excavation and preparing to build the foundation and approach slab for the new bridge.
See the agenda at: s6.goeshow.com/apta/tfc/202...
See the agenda at: s6.goeshow.com/apta/tfc/202...
If you look down into HYCC-3 from the High Line, you'll notice the trench has a new look. We’re installing rebar to prepare for concrete pouring to form the tunnel box.
If you look down into HYCC-3 from the High Line, you'll notice the trench has a new look. We’re installing rebar to prepare for concrete pouring to form the tunnel box.
Check out our photo gallery for an up-close look at our active construction projects: www.gatewayprogram.org/photo-galler...
Check out our photo gallery for an up-close look at our active construction projects: www.gatewayprogram.org/photo-galler...
In addition to ongoing work reinforcing the riverbed in preparation for tunnel boring, the Hudson River Ground Stabilization team is now also removing the remains of Pier 68 to clear the path for the tunnel boring machines that will dig into Manhattan.
In addition to ongoing work reinforcing the riverbed in preparation for tunnel boring, the Hudson River Ground Stabilization team is now also removing the remains of Pier 68 to clear the path for the tunnel boring machines that will dig into Manhattan.
Read it here: mailchi.mp/gatewayprogr...
Read it here: mailchi.mp/gatewayprogr...
The 12th Avenue Shaft is beginning to take shape! Guide walls are being installed now in preparation for construction of the slurry wall.
The 12th Avenue Shaft is beginning to take shape! Guide walls are being installed now in preparation for construction of the slurry wall.
GDC is committed to being a good neighbor. Since the Hudson County Shaft is being built across the street from homes and businesses, we’re installing a noise barrier along the edge of the construction site.
GDC is committed to being a good neighbor. Since the Hudson County Shaft is being built across the street from homes and businesses, we’re installing a noise barrier along the edge of the construction site.