Matt Dursh
banner
mattdursh.bsky.social
Matt Dursh
@mattdursh.bsky.social
Find me on X @mattdursh.
Thanks for reading my 🧵. I am a Professional Engineer, Bridge Designer, and Design-Build Project Manager.

Designing and building bridges over water is my career specialty.

I will continue to provide updates on the rebuild of the Francis Scott Key Bridge in Baltimore, MD. 7/7
January 1, 2025 at 11:11 PM
The Francis Scott Key Bridge rebuild is being done as a Progressive Design-Build method of project delivery.

The project is in the Preconstruction phase which advances the design, determines the full scope of work, and agrees on a Guaranteed Maximum Price for the work.

6/7
January 1, 2025 at 11:11 PM
Demolition work to remove the remaining Francis Scott Key Bridge will begin later in the Spring.

Work is for a turn key contract for on-land demolition, meaning one contractor will deliver the full services on land.

Over water demolition is subcontracted in segments. 5/7
January 1, 2025 at 11:11 PM
Land surveying will obtain topography and elevations of the project site.

An underwater survey called bathymetric will be done using sonar tech to map the mudline.

This photo is a side scan sonar of the collapsed Francis Scott Key Bridge after the Dali hit the bridge. 4/7
January 1, 2025 at 11:11 PM
Soil is carefully collected from the sampler, visually classified, and then sent to a lab to test it's properties.

The blow counts and properties will be used by the Francis Scott Key Bridge Geotechnical and Structural Engineers to design foundations for the new bridge.

3/7
January 1, 2025 at 11:11 PM
A soil investigation will be performed to determine the characteristics of soil to support the Key bridge.

Samples are collected using a Standard Penetration Test (SPT).

A heavy weight is dropped from a height to push the sampler into the ground while counting blow counts. 2/7
January 1, 2025 at 11:11 PM
The fire started the morning of November 1st, 2024 in Cincinnati, Ohio.

The bridge is currently stabilized and demolition of the damaged spans will begin after Thanksgiving.

Will need to do a 🧵 on this one in the future.
November 27, 2024 at 11:03 PM
The engineers of the Francis Scott Key Bridge can determine pile capacity in various ways.

While pile driving the capacity, stresses, and more info is calculated in real time.

After driving, a static load test can be done to verify the actual capacity of the steel pile.

4/4
November 27, 2024 at 1:49 AM
A Test Pile program verifies the soil that supports a bridge provides the necessary capacity to resist the loads from the structure.

The Francis Scott Key Bridge rebuild will use a Load Test Monitoring Geotechnical Consultant to determine capacity of the driven steel piles.

3/4
November 27, 2024 at 1:49 AM
Bridges are supported on deep foundations that transfer loads from the structure to earth.

The Francis Scott Key Bridge rebuild will use driven steel piles as the deep foundation.

Early Works construction for the Test Pile Program includes welders and rolled steel shapes.

2/4
November 27, 2024 at 1:49 AM
You are welcome. Thanks for the comment.
November 25, 2024 at 1:42 AM
I will continue to post details about the collapse of the Francis Scott Key Bridge and the upcoming rebuild of the Key Bridge.

I am bridge designer, Professional Engineer, and design-build design manager of heavy civil infrastructure projects.

Thanks for reading my 🧵. 9/9
November 24, 2024 at 7:21 PM
The rebuild of the Francis Scott Key Bridge is also likely to use a hollow reinforced concrete column as the pier substructure.

The channel piers of the replacement Key Bridge will be protected against vessel collision.

Anticipate the use of rock islands and dolphins. 8/9
November 24, 2024 at 7:21 PM
Would the Francis Scott Key Bridge still be standing if Pier 17 was solid?

No, the forces caused by the allision far exceeded the column's capacity.

To protect bridges against vessels the size of M/V Dali a pier protection system is used to run aground the ship first. 7/9
November 24, 2024 at 7:21 PM
Tension is resisted by the rebar. The further away the steel is from the concrete face, the more structural capacity it offers.

The reinforcing steel "works best" when it is near the outside of the section.

This is the fundamentals of reinforced concrete design. 6/9
November 24, 2024 at 7:21 PM
Concrete works well in compression, but has little tension capacity.

The hollow section provided enough area of concrete to resist the maximum compression loads.

By using a hollow pier section, the Key Bridge engineers reduced the weight of the column legs by about 50%. 5/9
November 24, 2024 at 7:21 PM